After some much needed rain, road crews in District 1 are back to work. Last week, the team ripped from Oklahoma 277 to Watts Road early in the week and finished out the week ripping on 75th Street on Cleeman, heading from North Drive to Wolfe Road.

This week, weather permitting, crews will begin ripping and recycling from Watts Road to North Drive. Work will continue on the north side of Elgin, working east and west.

Thank you for your continued patience as we work to improve the roads in the district. Just a reminder ... the roads are being ripped now, covered with gravel, and will be oiled and chipped this summer. Please pay attention to road signs for your safety and the safety of workers on the roads.